BrightBooks | Making Tax Digital for Income Tax Known HMRC issues affecting MTD quarterly updates What you may see, what it means and what to do |
Last reviewed: 23 November 2026. Based on HMRC information up to 20 November 2026.
HMRC has reported a number of live service issues that can affect Making Tax Digital for Income Tax (MTD for IT) quarterly updates. These issues sit within HMRC’s systems rather than in BrightBooks. This article explains what you may see, what HMRC is doing about each issue and what you can do in the meantime. We update it as HMRC shares new information.
Issues at a glance
| HMRC reference | Issue | Status |
| MTD-24520 / 24742 / 24735 | Cannot submit Q2 after filing Q1 | Under investigation |
| MTD-24506 | Quarterly obligation not marked as fulfilled | Under investigation |
| MTD-24699 | Obligations show as unfulfilled after ceasing a business | Fix due December 2026 |
| MTD-24171 | 503 error retrieving 2024/25 self-employment period | Fix due December 2026 |
| MTD-23940 | Matching Resource Not Found on Q1 submission | Under investigation |
| MTD-23474 | Obligation not fulfilled after a reporting type election | HMRC correcting manually |
| MTD-20250 | Reporting type not showing correctly in tax account | Monitoring |
Before you contact us
A few quick checks resolve many quarterly update queries:
- Check the dates covered. An obligation is only marked as fulfilled when your submission covers the whole quarter. Confirm that the start and end dates cover the full period before you assume there is a fault.
- Check the reporting type. New MTD customers default to standard reporting, so you do not need to make an election unless you are changing to calendar reporting. You cannot change the reporting type after you have submitted, so make sure it is correct before your Q1 submission.
- Make the election first, then submit. If you are choosing calendar reporting and submitting Q1 in the same sitting, complete the election first. Wait for your obligations to update in BrightBooks, then make the submission.
- Check your agent access. Supporting agents have restricted access and receive a 403 Not Authorised error on restricted HMRC services. If you are acting as a supporting agent, this is expected rather than a fault.
Issue details
Cannot submit Q2 after filing Q1 (MTD-24520, MTD-24742, MTD-24735)
What you may see: You filed Q1 successfully, but when you submit Q2 you receive the error Rule_Start_Date_Not_Aligned.
Status: New this week. HMRC is investigating why these submissions are failing and has not yet given a workaround.
What to do: First, check whether the error relates to an opt-out in 2025/26 (see “Rule_Start_Date_Not_Aligned_To_Reporting_Period” below). If it does not, contact our Support team and tell us the date you filed Q1 and the exact error message.
Quarterly obligation not marked as fulfilled (MTD-24506)
What you may see: You submitted a quarterly update, but HMRC still shows the obligation as unfulfilled.
Status: Under investigation. HMRC has identified the affected customers and is fulfilling their obligations manually while it schedules a fix. There is no change this week.
What to do: Check that your submission covers the whole quarter, then contact our Support team if the obligation is still open. You do not need to resubmit.
Obligations show as unfulfilled after ceasing a business (MTD-24699)
What you may see: You submitted your obligations, then ceased the business, and the obligations now show as unfulfilled.
Status: HMRC has set a target release date of December 2026 for the fix.
What to do: Do not resubmit. HMRC will reject it with the error RULE_SUBMISSION_END_DATE_CANNOT_MOVE_BACKWARDS. Contact our Support team so we can report your case to HMRC.
How to avoid it: If an income source ceases, submit from the start of the tax year to the date the income source ceased, not to the end of the quarter in which it ceased.
503 error retrieving the 2024/25 self-employment period (MTD-24171)
What you may see: A 503 error when BrightBooks asks HMRC for your self-employment period for the 2024/25 tax year.
Status: HMRC is still investigating and the target release remains December 2026. Only the 2024/25 tax year is affected.
What to do: No action is possible on your side. Please try again after HMRC releases its fix, or contact our Support team if you need help in the meantime.
Matching Resource Not Found on a Q1 submission (MTD-23940)
What you may see: The error Matching Resource Not Found when you submit Q1. This happens when the income source is not held on one of HMRC’s systems.
Status: Investigations are ongoing. HMRC is correcting affected records while it looks for the root cause. There is no change this week.
What to do: There is no workaround you can apply. Contact our Support team with your details so we can help get your record corrected.
Obligation not fulfilled after a reporting type election (MTD-23474)
What you may see: You chose calendar reporting and submitted straight away, and the obligation is not showing as fulfilled.
Status: HMRC is still marking affected obligations manually. It has also asked software providers to add a short delay between a reporting type change and the submission. We are reviewing this change on our side.
What to do: Make the election, wait for your obligations to update in BrightBooks and only then submit. If you have already submitted and the obligation is open, contact our Support team.
Reporting type not showing correctly in your tax account (MTD-20250)
What you may see: Your digital tax account shows standard reporting when you elected calendar reporting.
Status: HMRC last reported that it had corrected the affected records. We are continuing to monitor this issue.
What to do: Check that the correct reporting type is shown before you make your Q1 submission, because it cannot be amended afterwards.
Information note
Rule_Start_Date_Not_Aligned_To_Reporting_Period
This error is not a live service issue. Customers using calendar reporting may see it when they submit Q2 if they opted out for 2025/26 after making the calendar election. In that case, their 2026/27 obligations run from 6 April 2026 to 31 March 2027. If the calendar election was made after the 2025/26 opt-out, the 2026/27 obligations run from 1 April 2026 to 31 March 2027 instead. Please check which applies to you before you contact us.
Planned HMRC service downtime
HMRC’s services will be unavailable from 5pm on Friday 27 November to 9am on Monday 30 November 2026. Please avoid submitting during this window and plan any quarterly updates due around that time accordingly.
Need more help?
If your issue is not covered here, or you have followed the steps above and the problem remains, contact our Support team and include the HMRC reference above (where there is one), the exact error message and the date of your submission.
Contact Support